Power plant renovations planned
•June 26, 2024•
by Sharon Barricklow
The Sullivan City Council moved forward last week with plans to renovate equipment at the City Electrical Plant.
“We need to get on the stick here to get this done,” Commissioner Mike Kirk said.
At issue is a Colt-Pielstick engine necessary for the operation of the electric plant. The engine, originally put in service in 1973, was last overhauled in 1989. With only one company in the country, Fairbanks-Morse, doing the work, the council agreed to waive the bidding process and accept the estimate of just over $500,000 to do a complete engine overhaul.
Kirk said the engine will be off line for six to eight weeks during the process and that Fairbanks-Morse is estimating a 12 to 18 month time frame before they can begin work.