Commissioner Sherwood Presents Options for Project
•March 2, 2022•
by Crystal Reed
NP Writer
During Monday’s meeting of the Sullivan City Council, Commissioner Abbey Sherwood presented two possible options for a new city building project. She said they are down to two options in terms of build and location. There is a teardown and rebuild of a two-story building with an elevator at the current location near the square.
It would be $125,000-$150,000 for an elevator. “This option would put limitations on our needs and potential,” she said. The other option is a one-level building with the building going north into the old Jibby’s lot.
There were concerns because of the utilities in the alley. A review with sewer foreman Justin (Bubba) Farris was done, and a cost estimate including the move of utilities was estimated at $30,000. The repair of the road plus the purchase of the Jibby’s lot would be $75,000. They have a budget of $2 million budgeted out of TIF.